Which list of stages applies to your building?

Georgian law uses "stage" twice. The permit procedure has its own stages, covered in our guide to checking a construction permit. This page follows the stages of the works themselves.

That list is in Article 20 of Government Resolution No 255 of 31 May 2019. The works are split into "queues", at least preparatory and main, and each queue into stages fixed in the construction organisation project. That project may merge, split or drop stages according to the building's class. Two rules matter: the permit must name "the stages of construction (supervision)" for the building (Article 25(2)), and keeping to their sequence is mandatory (Article 26(4)). Ask for the permit page with the stage list before you sign.

We checked these articles against the consolidated text as amended to 16 February 2026; have a lawyer confirm any article before relying on it.

What are the official construction stages, in order?

In the order of Article 20, with our suggestion of what to ask for once a stage is reported done.

Construction stages under Resolution No 255 Resolution No 255 (as amended to 16 February 2026), Art. 20(4) and 20(6); last column is our suggestion
StageWhat happensAsk for or look at
1. Site preparationClearing, demolition, moving underground utilitiesSite board with the permit number
2. Setting outMarking the building's main axes on the groundFootprint against your contract's site plan
3. EarthworksDigging the pitEngineering-geological survey conclusion
4. Foundation bedPreparing the baseName of the technical supervisor
5. FoundationsCasting the foundationsPhotos of the steel; registered protocol
6. Structure to zero levelLoad-bearing structure up to ground-floor levelRegistered protocol
7. Structure above groundRecorded at most every 7.0 metres of height or in whole storeysA protocol for each section
8. RoofRoof structure and roofingRegistered protocol
9. Non-load-bearing structuresPartitions and infill wallsPhotos of wall fixings before plaster
10. Local networksThe building's shared engineering networksUtility connections applied for
11. EquipmentFor example liftsLift make named in the specification
12. Exterior finishingFacade worksFacade against the board's image
13. LandscapingWorks on the plotYard against the greening project

Which papers prove that a stage is finished?

  • The site board. Within 10 days of the permit it must show the issuing body, permit number and validity, the start and completion dates of construction, and the building's function and architectural appearance (Resolution No 255, Article 19(4)). A missing or incomplete board costs GEL 2,000 in Tbilisi and GEL 400 in other cities (Spatial Planning Code, Article 134). The permit number on it should match your contract.
  • Drawings on site. A certified copy of the construction documentation must be kept at the site from the start (Article 26(1)(a)). No rule we found obliges the developer to show it to buyers, but ask.
  • The supervisor's stage file. On Class III-IV sites the technical supervisor must send the public supervision body documentation on the completion of each stage (Spatial Planning Code, Article 119(7)(b)). An older rule that the permit holder warn that body 10 days before a stage ends (Article 20(9)) was repealed in April 2021.
  • The stage protocol. Drawn up after an on-site check against the permit (Article 20(10)) and signed by the permit holder and another authorised participant (Article 26(5)). For Class II-IV buildings it goes in writing to the body that will commission the building before the next stage ends, and has legal force only once registered there (Article 26(6)).

Protocols are filed with the city, not the Public Registry, and we could not confirm that buyers can obtain them from the city, so ask the developer for a copy of each. Missing protocols surface at the end; see commissioning.

Who checks the works, and who do they answer to?

The Spatial Planning Code names three kinds of supervision (Article 117): public, by the municipality; technical, by an accredited inspection body or certified expert; and safety supervision.

Who supervises a Class III or IV building Spatial Planning Code, Arts. 117-121
SupervisorAppointed byRole
Technical supervisorThe developer; mandatory for Class III-IV (Art. 119(4))Inspects, keeps records, files each stage's documents with the public body; insured and liable to the permit holder (Art. 119(6)-(7))
Public supervision bodySet by the city council (Art. 118(2))Checks permit conditions, safety and commissioning; may enter the site and demand papers (Art. 118(1), (5))
Safety personPermit holder or builder (Art. 121(1))Reports safety breaches to the public body (Art. 121(2))

Where a technical supervisor works, the public body acts by random selection, on risk analysis, or on a complaint from an interested person (Article 118(3)). Every year it must supervise no less than 10% of all Class III-IV buildings permitted in the previous year (Article 118(4)). After a positive conclusion from the technical supervisor, it may inspect within 15 working days; then the stage "is considered accepted" (Article 120(1)). So the inspector signing off your stages is paid by, and answers to, the developer; your lever is a complaint to the city.

In Tbilisi this is City Hall's Municipal Inspection. Its own pages on tbilisi.gov.ge say it inspects building sites, suspends and fines breaches, controls construction stages and commissions finished buildings, issuing the act; about 7,000 buildings had been commissioned through it since 2018 (BM.ge, August 2025). Batumi has the Batumi Municipal Inspection, which must check suspended sites at least monthly and keep a register of them (City Council Resolution No 7 of 30 March 2023); which Batumi body issues the commissioning act is not confirmed. The national Technical and Construction Supervision Agency does not supervise ordinary apartment blocks. See also Batumi high-rise quality.

What can you look up yourself as the works progress?

Public records by stage Law on the Public Registry, Art. 15-6; Order No 487, Art. 16 (as amended 2024); NAPR fees checked 13 October 2026
MomentWhat should appearWhere
Before payingPlot owner, mortgages, seizures, bansRegistry extract, GEL 13 online
Land-use terms issuedFirst permit decision; a promise of a future flat becomes registrable (Art. 15-6(10))tas.ge (Tbilisi)
Permit issuedPermit number, date, amendmentstas.ge; the site board
Works under wayBuilding and units registered as under construction (Art. 15-6(1))Registry extract
CommissioningRecords of every unit updatedRegistry extract

The Tbilisi Architecture Service's decision search on tas.ge accepts a cadastral code (format XX.XX.XXX.XX, as on the registry extract), an application or decision number and dates; we have not tested how complete its results are. City Hall launched a map of commissioned and suspended sites in November 2025; whether it is a layer of maps.tbilisi.gov.ge is not confirmed. Note that without construction documentation on file, the building is left off the extract and the cadastral plan (Art. 15-6(2)), so an extract still showing bare land months after the permit deserves a question. For Batumi we found no similar lookup; see construction permit.

Earthworks and foundations: what should you photograph?

Nothing here replaces an engineer. The rules below come from the seismic norm PN 01.01-09 (Order No 1-1/2284 of 7 October 2009) and tell you what to ask, not how to judge the work. The full seismic picture is on our earthquake building code page.

  • Soil. Ask for the engineering-geological survey, required for Class II-IV (Resolution No 255, Article 21(2)), and its soil category. High-rise buildings are not allowed on category III soils (PN 01.01-09, Article 10(12)).
  • Foundation type. Frame buildings on category III soils need a reinforced-concrete cross-strip or solid slab foundation (Article 7(10)).
  • Steel before concrete. Photograph the reinforcement, dated and with a tape measure in view, and send it to an engineer before the pour.
  • Paper before money. Get the registered protocols for stages 3 to 5 before paying anything linked to "foundations complete".

The frame: what can you check floor by floor?

Above ground, a tall block should produce a series of protocols, one per section of at most 7.0 metres or per whole storeys. Compare floors cast with the board's dates. An engineer can often check these rules from photographs of exposed steel:

  • Columns on the outer line. An "incomplete frame", with masonry perimeter walls and a rigid frame only inside, is not allowed (Article 10(6)).
  • Column ties. In frames at design intensity 8 or 9, as in Tbilisi, ties may be no further apart than half the column's smallest side (the full side where load-bearing shear walls are used) and at least 8 mm thick (Article 9(3)), with ends anchored into the concrete core (Article 9(4)).
  • Joints. Closed ties of at least 8 mm, at most 100 mm apart, where no diagonal reinforcement is required (Article 10(11)).
  • Gaps between blocks. Adjoining blocks need a full-height seismic joint, at least 30 mm for a building up to 4 m high plus 20 mm for each further 5 m (Article 6, paragraphs 3-4).

After the roof: which stages are still left?

With the roof on, five official stages still remain.

  • Infill walls. They need a flexible connection to the frame, a gap of at least 20 mm from the columns and an anti-seismic belt at slab level or at the top of the windows (PN 01.01-09, Article 10(9)). Photograph the fixings before plastering.
  • Parapets and railings. Elements that could hurt people if they fell must be designed with their fixings for seismic load (Article 6(8)). Ask how balcony railings are anchored.
  • Lifts and fire systems. Their test acts belong in the commissioning file.
  • Facade and yard. Compare them with the board and with the greening board, required where the zone sets a minimum greening coefficient (Code Article 110(1-1)).

Your own flat comes last: finishing levels are in black, white and green frame, the inspection in the handover checklist, and the paper you sign in the handover act.

How can your payments follow the stages?

We found no published Georgian developer contract template with payments tied to construction stages. Published plans run by the calendar: Otar Nadaraia, a former Vice Governor of the National Bank, told Sovanews in October 2026 that buyers pay "over a period of two to three years", with down payments "as low as 0%". Our suggestion is to name the official stage in each instalment clause and make the money due on receipt of that stage's registered protocol:

Linking instalments to stages Our suggestion, based on Resolution No 255, Arts. 20 and 26
Instalment due onEvidence
FoundationsRegistered protocol
Structure to zero levelRegistered protocol
Structure to a named floorProtocol for that section
RoofRegistered protocol
CommissioningCommissioning act
Final paymentExtract showing your flat

Whether sale rules or contract-for-work rules govern a developer contract is not settled in the texts we read, so have a lawyer classify yours. Only if it is a works contract do these Civil Code defaults apply: the client pays once the work is done unless the contract provides for payment in parts (Article 648), and a client who accepts work with a known defect without objecting has no claim for that defect (Article 652). Either way, be wary of stage acceptance forms offered to buyers. See the developer contract clauses and instalment plan terms.

How long should each stage take?

No analyst we checked, Galt & Taggart and Geostat included, publishes an average build time for Tbilisi or Batumi, so we quote none. The yardstick is the developer's own: the permit term, "a reasonable term" from the construction organisation project (Code Article 111(1)), and the completion date on the board. In Galt & Taggart's September 2026 Tbilisi survey, flats were on sale in projects due in 2026, 2027 and 2028-29, already 82%, 73% and 62% sold; its July 2026 Batumi survey ran to 2029. As examples only, a few listing pages we saw in 2026 gave planned build times of about four years for blocks of 20 floors or more, on developers' own dates; that is not an average. Pipeline data: our supply tracker.

What if the site stops between stages?

  • Permit expired, works unfinished. A new permit with a schedule for the remaining works is required (Code Article 112).
  • Site idle without conservation. Abandoning a site in breach of the conservation rules is fined GEL 20,000 for Class III-IV in Tbilisi and GEL 2,000 in other cities (Article 135).
  • Suspension order ignored. GEL 50,000 in Tbilisi (Article 136); the public body must check a suspended site at least monthly.
  • Permit conditions breached. GEL 10,000 for Class III, GEL 15,000 for Class IV, more in Tbilisi heritage zones (Article 132).

None of these fines compensates a buyer, but each leaves a public trace. Remedies are in when the developer is late; causes and scale in construction delays in Georgia.

Risks and exceptions

  • Paying by the calendar alone. Money keeps flowing while the site stands still.
  • "Frame finished" without a protocol. A sales message, not evidence.
  • Trusting the developer's inspector. It answers to the developer.
  • Missing the photographs. Steel and fixings vanish under concrete and plaster.

Frequently asked questions

How many construction stages are there?

Resolution No 255 lists two preparatory and eleven main-works stages; the permit states the list for each building.

What is a stage protocol?

The signed record that a stage is complete and matches the permit. For Class II-IV it is valid only once registered with the commissioning body.

Does the city inspect every stage?

No. It may inspect within 15 working days of the supervisor's positive conclusion; otherwise the stage counts as accepted.

Must the developer show me the protocols?

We found no such rule. Make copies a condition of each instalment.

Next step

Ask a question on WhatsApp. We reply within one working day.

Write on WhatsApp

Stages matter only once the developer passes scrutiny: start with how to check a developer.

Sources

  1. Resolution No 255 on issuing construction permits and recognising buildings fit for commissioning, Government of Georgia, Legislative Herald of Georgia, 31 May 2019, consolidated to 16 February 2026 (accessed 3 November 2026)
  2. Spatial Planning, Architectural and Construction Activities Code of Georgia, Legislative Herald of Georgia, consolidated 25 June 2026 (accessed 3 November 2026)
  3. Construction norms PN 01.01-09 "Seismic-resistant construction", Order No 1-1/2284, Legislative Herald of Georgia, 7 October 2009 (accessed 3 November 2026)
  4. Civil Code of Georgia, Legislative Herald of Georgia, consolidated text (accessed 3 November 2026)
  5. Law of Georgia on the Public Registry, Legislative Herald of Georgia, consolidated 1 April 2026 (accessed 2 November 2026)
  6. Instruction on the Public Registry, Order No 487, Article 16 as amended by Order No 993, Legislative Herald of Georgia, 26 March 2024 (accessed 3 November 2026)
  7. Informational services fee, National Agency of Public Registry (accessed 13 October 2026)
  8. Resolution No 7 on control by the Batumi Municipal Inspection over construction-suspension acts, Batumi City Council, 30 March 2023 (accessed 3 November 2026)
  9. Search the Service's decisions, Tbilisi Municipality Architecture Service (accessed 3 November 2026)
  10. Municipal Inspection: tasks and functions, Tbilisi City Hall (accessed 3 November 2026)
  11. Control of construction stages and Commissioning, Municipal Inspection, Tbilisi City Hall (accessed 3 November 2026)
  12. Tbilisi reviewing commissioning of 230 residential buildings to support 10,000 families - Kaladze, BM.ge, 6 August 2025 (accessed 3 November 2026)
  13. Tbilisi launches interactive map to track construction status and protect homebuyers, BM.ge, 27 November 2025 (accessed 3 November 2026)
  14. Who can afford real estate in Tbilisi: mortgages, installment plans and new regulations, Sovanews, 8 October 2026 (accessed 1 November 2026)
  15. Tbilisi Residential Real Estate, August 2026, Galt & Taggart, 23 October 2026 (accessed 2 November 2026)
  16. Batumi Residential Real Estate, 2Q26 overview, Galt & Taggart, 14 August 2026 (accessed 2 November 2026)

Change log

  • - Checklist published from Resolution No 255, the Spatial Planning Code, the seismic norm PN 01.01-09 and the Public Registry rules.